Specified inspections
Where the Agreement specifies witness points, hold points or the like to be observed during construction of works, the consultant must make suitable arrangements with us to enable adequate inspection to take place as may be necessary, at mutually agreed times.
We won't accept works unless specified inspection procedures have been completed to our satisfaction.
Contractor activity
The consultant must:
-
advise us if the contractor vacates the site
-
give us two working days notice prior to the contractor recommencing work.