The Owner must provide easements reserves in favour of us over Works constructed as part of the Agreement or as specified within the Offer.
Easements and reserves may also be required over excavation in accordance with 'Excavations' or 'Floodplains'.
Before we'll issue a Certificate of Completion or Letter of Release (authorisation to the Council to issue a Statement of Compliance):
-
the Owner must've provided evidence appropriate Creation of Easement documentation has been lodged with the Office of Titles to enable easements within the development to be registered in favour of us
-
easements and reserves within the development must be specified in favour of us on the certified plan of subdivision
-
the Owner must've provided evidence appropriate Creation of Easement documentation has been lodged with the Office of Titles to enable easements over land external to the development to be registered in favour of us
-
Evidence must be provided to us the easement and the as-constructed asset are aligned with one another.
We recommend the use of special easement MCP0821 or MCPAA821 for the creation of easement over our assets.